Air-conditioning compliance: which documents do you need?

F-gas certificates, RAMS, test records and handover documents. What each is for, when it applies and what to agree with your client.

Reading theme
Technical pen drawing of a contractor pointing to the wall-mounted air-conditioning unit while a client in a charcoal jacket reviews an open installation record; emerald accents highlight the equipment and binder on a white background.

Check what your client needs

Start with these documents. Confirm the client’s list before work starts; the requirements depend on the system, site and work involved.

  1. 01 / Before work

    Company F-gas certificate

    Company certification for the F-gas work.

  2. 02 / Before work

    F-gas qualification

    The engineer’s qualification for the work involved.

  3. 03 / Before work

    Site-specific RAMS

    The risk assessment and method statement for this job.

  4. 04 / During work / handover

    Commissioning report

    Recorded tests, settings and system performance.

  5. 05 / At handover

    Electrical certificate

    Installation or minor works certificate, as appropriate to the electrical work.

  6. 06 / At handover

    O&M manual

    Operation and maintenance: equipment details, user instructions and upkeep.

Why does the client need these documents?

  • Legal requirements. The company and engineer need the appropriate certification and qualifications for the F-gas work they do.
  • Contract requirements. Test records show whether the system meets the agreed specification.
  • Site access. The client may need RAMS, insurance documents or permits before work starts.

Sources: 1, 2

Check the site before work starts

Confirm permissions and get the building information needed for the installation.

  1. Architectural sketch of a contractor checking unit positions and pipe routes on an office floor plan.

    01Plans and permissions

    Agree unit positions, routes, power supply and maintenance access. Confirm any landlord consent, planning permission or building-control approval needed.

  2. Architectural sketch of a surveyor using a services detector against an office wall and holding a clipboard.

    02Building surveys

    Get asbestos and service information for the work area before drilling or opening walls and ceilings. Arrange further surveys where needed.

Who prepares the construction phase plan?

  • One contractor: that contractor prepares it.
  • More than one contractor: the principal contractor prepares it.

RAMS does not replace this plan.

Sources: 3, 4, 5

Make your RAMS specific to the site

Use the site plans and survey findings to describe the work. Record the agreed controls for these four areas.

Architectural pen cutaway of an office installation showing the indoor air conditioner, power isolator, pipe route through the wall, outdoor condenser on supports and green barriers marking the work area beside an office desk.
Indoor unit, power isolation, wall opening and outdoor unit, with the work area marked by barriers. Illustrative model; plan the details for the actual site.
Walls and ceilings
Record the survey information used and how openings will be made, sealed or fire-stopped.
Power supply
Record the isolation and testing arrangements, the competent person and agreed shutdown times.
Outdoor unit
Describe lifting, supports, access and any work at height, including space for maintenance.
Office staff
Record work boundaries, dust controls, delivery routes and working hours. Show how escape routes stay clear.

Sources: 3, 4, 5

Records to keep during the work

Agree any client inspections before work starts. Put the equipment reference, location and date on each record.

Architectural sketch of an engineer recording air-conditioning test readings on a clipboard beside an outdoor unit, with a camera and route drawing nearby.
Keep photos, test results and commissioning records for the installed system.
  1. 01Before closing up

    Record pipe routes, openings and relevant fire-stopping details as agreed. Photos support inspections but do not prove compliance on their own.

  2. 02During testing

    Keep the pressure, leak, evacuation, drainage, electrical and functional results that apply to the job. Record actual readings against the manufacturer’s requirements and agreed specification.

  3. 03Commissioning

    Record settings, controls and performance against the agreed design. Fix defects or list what still needs to be done.

For work in England, confirm which Part L edition and Building Regulations process apply. Agree who submits any required commissioning notice and gives system information to the owner.

Sources: 6

Documents to give your client

Agree which of these the client needs. Not every item is a legal requirement for every job.

Air-conditioning installation

Handover checklist

Client documents01

Give the client the final documents, demonstrate the controls and explain maintenance and any refrigerant duties. Record receipt, acceptance and who will operate the system. Keep a copy.

Sources: 6, 7